Bitumen Logistics and Shipping: Modes, Transit, Port Requirements and Landed Cost

Bitumen ships in three forms: packed in drums or bags inside a container, in an insulated tank container, or as a bulk parcel pumped into a heated shore tank. This page sets out what each mode requires at the destination port, what a long ocean transit does to the binder, and how a landed tonne is actually built up from product, packing, freight, duty and the charges that appear afterwards.
30,480 kgMax gross, 20' container (ISO 668)
20–25 MTBitutainer payload
130–160 °CTypical discharge temperature
2713.20HS code, petroleum bitumen
The three modes

How bitumen actually moves from filling plant to job site

There are only three ways to ship bitumen, and the right one is chosen by what the buyer has at the receiving end — not by what looks cheapest per tonne at the load port.

Every bitumen shipment is a compromise between three things that pull against each other: the freight cost per tonne, the equipment the buyer has at destination, and how fast the cargo can be turned into usable binder. The cheapest freight per tonne is bulk, and bulk also demands the most infrastructure. The lowest infrastructure requirement is drums, and drums carry the highest cost per tonne and by far the most labour. Everything else on this page follows from that tension.

1. Containerised: drums, jumbo bags and poly bags

The binder is filled hot at the plant, allowed to set, and then moves as ordinary containerised freight on any liner service that calls at the load port. No special vessel, no special berth, no heated tank at either end. This is why containerised bitumen dominates trade into markets that have asphalt plants but no bitumen terminal.

The published loading figures used across this site are:

  • New steel drum, 150 kg net — 80 drums per 20-foot FCL, 12 MT net per container, about 84 containers per 1,000 MT.
  • New steel drum, 180 kg net — 80 drums per 20-foot FCL, 14.4 MT net, about 70 containers per 1,000 MT.
  • New steel drum, 185 kg net — 80 drums per 20-foot FCL, 14.8 MT net, about 68 containers per 1,000 MT.
  • Jumbo or poly bag, 1 MT — 20 bags per 20-foot FCL, 20 MT net, about 50 containers per 1,000 MT.

Two consequences follow from those numbers. First, what limits a bitumen container is the stack and the road, not the cube and not the container's own plate. Drums are stacked two tiers and no higher, because the binder softens in transit and a third tier deforms the drums beneath it; ten along the length by four across by two tiers is 80 drums, and the tonnage is simply whatever those 80 drums hold. One-tonne bags follow the same floor plan — ten down, ten on top, 20 bags and 20 MT. Both loads sit well inside what the box is entitled to carry: ISO 668 sets the maximum gross mass of a standard 20-foot container at 30,480 kg, the CSC plate on the individual unit governs, and a tare of around 2,250 kg leaves a payload in the region of 28 tonnes. Forty-foot equipment does not recover that headroom, because under ISO 668 it carries the same 30,480 kg maximum gross mass on a heavier tare, so its payload is lower still and a full 40-foot floor plan of drums would exceed it. What genuinely binds first is destination road and axle-weight law, which in several markets caps a single container movement below 20 tonnes of cargo — the reason 150 kg drums at 12 MT per box stay popular in places where 180 kg drums would otherwise be the cheaper packing per tonne.

Second, the drum tare is real weight that travels. A new steel drum weighs roughly 18–22 kg empty, so 80 drums of 180 kg net is 14.4 MT of binder and close to 16 MT gross before the container's own tare. That steel is paid for on the invoice, carried across the ocean, and then becomes a waste-disposal problem at destination. It is also the reason a drummed tonne lands dearer than a bagged tonne even when the product price is identical.

2. Tank container and bitutainer

A bitutainer is a tank built inside a standard 20-foot ISO frame, insulated and fitted with a heating system — commonly electric elements or a fuel-fired heater serving internal coils — and a bottom discharge outlet. Payload is 20–25 MT, so roughly 40 to 50 units carry 1,000 MT. Because the frame is ISO-compatible, it moves on the same liner services, the same gantry cranes and the same chassis as a dry box. No jetty, no shore hose, no terminal.

The trade-off is that the product arrives as a single 20-tonne mass of cold bitumen that has to be reheated before anything can be pumped out. That takes power or fuel, it takes a receiving tank, and it takes time measured in days rather than hours. The second trade-off is commercial rather than technical: the unit itself is an asset. Either it returns empty, and somebody pays for the repositioning leg, or it is bought outright with the cargo. Establish which arrangement is being quoted before comparing a bitutainer offer against a drum offer, because the two prices are not describing the same thing.

3. Bulk vessel with heated tanks

Bulk parcels move on specialised bitumen tankers or heated product tankers whose cargo tanks are insulated and fitted with heating coils, normally thermal-oil or steam served. The cargo is loaded hot, held hot for the whole voyage, and discharged by the ship's own pumps through a hose or hard-arm connection into shore tanks. Parcel sizes in this trade typically start around 1,000 MT and run into the several thousands depending on the vessel and how many buyers share the voyage.

Bulk is the cheapest way to move bitumen per tonne, with no packing cost at all and no waste to dispose of. It is also the only mode that requires a genuine receiving terminal: a berth the vessel can work, a discharge line that is short, insulated and heat traced, heated storage with the capacity to take the whole parcel, and a defensible way of measuring what came off. Under a charter party the vessel also brings laytime and demurrage into the contract, which is a category of cost that containerised shipments do not have.

Choosing between them

The decision is almost always made by the destination, not the origin. A contractor with a drum melter and a yard buys drums. A plant with a receiving tank and a pump buys bitutainers. A terminal or a large asphalt producer with a tank farm buys bulk and stops thinking about packing entirely. Where a buyer is moving from one tier to the next, the honest comparison is landed cost per tonne including the cost of getting the binder out of its packing and into the mixer, not the price on the offer sheet.

Mode comparison

Parcel sizes, container counts and what each mode demands

The same 1,000 tonnes of binder looks completely different depending on how it is packed. This table converts each mode into the numbers that drive a freight booking and the equipment list at destination.

Loading figures and destination requirements by shipping mode. Container counts are rounded up — a partial container still occupies a slot and still carries a full freight cost.
ModeTypical lot or parcelNet per unitUnits per 1,000 MTWhat the buyer must have at destination
Steel drums, 150 kg net1 FCL upward80 drums, 12 MT per 20' FCL84 containersForklift with drum clamp or slings, level hardstand, drum melter or decanter
Steel drums, 180 kg net1 FCL upward80 drums, 14.4 MT per 20' FCL70 containersAs above, with fewer drums to handle and dispose of per tonne
Steel drums, 185 kg net1 FCL upward80 drums, 14.8 MT per 20' FCL68 containersAs above; confirm destination gross and axle weight limits first
Jumbo or poly bag, 1 MT1 FCL upward20 bags, 20 MT per 20' FCL50 containersLifting beam or clamp, and a melting unit that accepts a whole bag
Tank container / bitutainer1 unit upward20–25 MT per unit40–50 unitsPower or fuel for reheating, a receiving tank, discharge connection
Bulk vessel, heated tanksTypically 1,000 MT and aboveParcel sizeOne part cargoBerth, traced and insulated shore line, heated storage, calibrated gauging
Drum and bag counts are the standard figures used across this site and hold for common drum dimensions. Verify them against the actual loading plan and the destination weight regime before committing to a shipment schedule, because a container that cannot legally leave the port gate is not a delivered tonne.
Destination

Port and terminal requirements at the receiving end

Most bitumen delays are not caused by the ship. They are caused by a receiving facility that was not ready on the day the cargo arrived.

1

Berth and reception line

For a bulk parcel the berth has to take the vessel and the discharge line has to be short, insulated and heat traced. A long, cold jetty line will stiffen with product in it and turn a routine discharge into a blocked pipeline.

2

Heated shore storage

Tanks with thermal-oil or steam coils, sized for the whole parcel plus the heel already in tank. Hold a paving grade at about 150–165 °C while it is being worked, drop below 150 °C for anything longer, and treat 180–190 °C as an absolute ceiling that is never to be exceeded.

3

Pumps and hoses

Gear pumps sized for the viscosity at the actual discharge temperature, and hoses rated for hot product. Lines must be blown or flushed clear after discharge, because bitumen left standing in a cold line sets where it stands.

4

Drum and bag handling

Clamp truck or slings, a level hardstand, covered storage away from standing water, and melting capacity that matches the delivery rate. Eighty drums per container is a lot of individual lifts if the yard is not laid out for it.

5

Quantity determination

A weighbridge for drummed and bagged cargo, or a calibrated tank table plus verified temperature for bulk. Agree the basis before arrival; a hot volume reading and a contract in tonnes are not the same measurement.

6

Safety and permits

Safety Data Sheet on site, bunded tank area, fire cover and hot-work control. If hot bitumen reaches skin, flood the area with clean cold running water and keep it running for at least 20 minutes; adhered bitumen is never peeled off or stripped with solvent, and its removal is a decision for medical staff.

On arrival

Loading temperature, condition on arrival and what it takes to discharge

The single most useful question a buyer can ask before booking is simple: in what physical state will this cargo be standing on my yard, and what do I have to do to it before it enters a mixer?

Typical loading temperatures and the discharge sequence each mode requires at destination.
ModeFilling or loading temperatureCondition on arrivalDischarge equipment requiredReheating before use
Steel drumsFilled at about 140–160 °CSolid at ambient. Drums may be soft, bulged or seeping at the lid after a hot-climate transitClamp truck or slings, hardstand, drum melter or decanter with drum tipping frameYes — every drum must be fully melted
Jumbo and poly bagsCast at about 140–160 °CSolid block inside the bag; bags may deform and adhere to each other under stack load and heatLifting beam or crane, melting unit that accepts the whole bagYes — a jumbo bag's woven outer and release liner are stripped and the block charged; a meltable poly bag goes into the melter whole
Tank container / bitutainerAbout 150–165 °CWell below pumping temperature unless the unit was heated in transit; commonly a single cold massBottom outlet connection, transfer pump or gravity drop, heated receiving tankYes — on-board heating brings the product back over a period of days, not hours
Bulk vessel, heated tanksLoaded at about 150–165 °CHeld hot by cargo coils throughout the voyage; typically discharged in the 130–160 °C rangeHose or hard arm, insulated and traced shore line, heated shore tank, gaugingNo, provided cargo heating has been maintained for the whole voyage
Bitumen becomes difficult to pump as it cools, and the practical pumping window for a paving grade sits around 130–160 °C. A bulk parcel that has lost heat because a coil failed mid-voyage will discharge slowly, and slow discharge on a chartered vessel converts directly into demurrage. Ask for cargo temperature logs on arrival, not just at load port.
Transit

What a long transit does to the product

Transit time on the bitumen trade lanes ranges from under a week on short Gulf-to-South-Asia routings to well over a month where transhipment is involved. Time is not neutral for this cargo.

Ask for the routing, not just the sailing date. A direct service and a service with one transhipment can quote similar door-to-door windows and then behave completely differently, because every transhipment adds a port call, a lift, a stow decision and an opportunity for the box to miss a connection. For planning, treat transhipment legs as the main source of schedule risk, and build float into the date the melting unit is booked rather than into the date the vessel sails.

Heat history is cumulative

Bitumen ages by oxidation, and oxidation runs faster the hotter and longer the binder is held. A bulk parcel held hot for several weeks has a heat history that a drummed cargo simply does not have. The effect is measurable in the same properties the specification is written in: penetration falls, softening point rises, and the binder becomes stiffer than the grade it was loaded as. It is the same oxidation mechanism the rolling thin film oven test (ASTM D2872) reproduces in the laboratory, although that test is calibrated to the short, hot exposure a binder gets in a mixing plant rather than to weeks in a cargo tank. It is also why long holds above about 150 °C are discouraged, and why the industry rule of thumb — hardening roughly doubles for every 10 °C of storage temperature — matters more on a bulk voyage than anywhere else. On a long voyage, ask what temperature the cargo was held at, not only what it was loaded at.

Containers get hot as well

A steel box standing on a terminal apron in the tropics is an oven. Interior temperatures well above ambient are routine, and they sit uncomfortably close to the ring-and-ball softening point of a normal paving grade, which for Bitumen 60/70 falls in the 49–56 °C band. The binder does not turn to liquid, but it softens enough to matter: drums bulge, lids weep at the seam, drums lower in the stack deform under the ones above, and bags slump and stick together. Cargo stowed under deck or in the middle of a stack has a much easier time than a box on the top tier in full sun. This is a real argument for tight, level stowage, proper dunnage and lashing, and for not letting a loaded container sit on a quay for weeks.

Water is the enemy, and it arrives free

Warm, humid air is sealed into a container at stuffing. As the box heats and cools each day it condenses on the underside of the roof and runs down onto the cargo. That water finds drum seams and lids, and it rusts them. It is also a genuine hazard downstream: water trapped at the bottom of a tank or a melting kettle flashes to steam when the product goes past 100 °C and can throw hot bitumen out of the vessel violently. Check drums for standing water before they go anywhere near heat, and check that a shore tank is dry before it takes a hot parcel.

Drum condition is a commercial issue, not a cosmetic one

Rusted, dented or leaking drums are a leading cause of disputes when a bitumen container is opened at destination, and reconditioned drums are a large part of why drums arrive in that state. Specify new steel drums explicitly in the contract. Have the loading photographed and have an independent inspector record packing condition, seal numbers and drum count at the load port, because once the box is opened at destination there is no clean way to establish whether damage happened in transit, at the terminal, or during discharge.

Every reheat cycle costs quality

The product that suffers most is the one that is heated, cooled, and heated again. Plan to melt once, gradually and uniformly, and to use what is melted. Two things must never happen at the melting point: flame against steel with no product behind it, and a heating coil or element running while any part of it stands proud of the binder. Both scorch the material at the metal face, which contaminates the whole batch and starts fires.

Cost structure

Where the money actually goes in a landed tonne

A price per tonne is not a landed cost. Between the filling plant and the mixer there are a dozen separate charges, they sit with different parties depending on the Incoterm, and only some of them move.

Landed cost components for an export bitumen shipment, with the party that normally carries each and how volatile it is.
Cost componentWhat it coversNormally carried byVolatility
ProductThe binder itself, ex-plant or ex-tankSeller, inside the offer priceHigh — tracks crude and heavy residue values
PackingNew steel drums, jumbo or poly bags, pallets and dunnageSeller, inside the offer priceMedium — driven by steel and resin prices
Inland haulage at originFilling plant to the load port or container yardSeller under FOB and aboveMedium — fuel and trucking capacity
Origin terminal handlingStuffing, lift-on, lashing, seals, weighbridge, port duesSeller under FOB and aboveLow — tariffed and published
Export documentationCertificate of origin, chamber attestation, export clearanceSeller under FOB and aboveLow
Third-party inspectionQuality, quantity and packing survey with sealed retained samplesAs agreed and stated in the contractLow — a small fraction of cargo value
Ocean freightThe container slot, or the vessel for a bulk parcelBuyer under FOB; seller under CFR and CIFHigh — the least predictable line in the whole build-up
Freight surchargesBunker adjustment, congestion, war risk, peak season, equipment imbalanceFollows whoever pays the freightHigh — can move between booking and sailing
Marine cargo insuranceLoss or damage cover under Institute Cargo ClausesBuyer under FOB and CFR; seller under CIFLow to medium — rises with route risk
Destination terminal handlingDischarge, lift-off, gate charges, documentation feesBuyer, other than under DPU, DAP and DDPLow — tariffed, but check it is not double charged
Import duty and taxesDuty on HS 2713.20 plus VAT, GST or equivalentBuyer, other than under DDPLow day to day, step changes with policy
Demurrage, detention and storageFree time exceeded at the terminal or on the box outside itWhoever caused the delay, in practice the consigneeVery high, and almost entirely avoidable
Discharge and reheatingDrum melting, bitutainer reheat, shore pumping, empty drum disposalBuyerMedium — energy cost and labour
Inland delivery at destinationPort to plant or site, including any escorted or permitted movementBuyer, unless the named place under DAP, DPU or DDP is inlandMedium — fuel and local haulage
Read the volatility column before you read the price column. Product, ocean freight and surcharges are the three lines that move enough to reverse the ranking of two offers between quotation and shipment. Terminal handling, documentation and duty are effectively fixed for the duration of a normal enquiry. Demurrage is the odd one out: it is the most expensive line on the table when it appears, and it is the only one that is entirely within the parties' control.
Commercial

Which lines move, who carries them, and where the clock costs money

Two offers on the same grade can differ by more in freight and destination charges than in the price of the binder. The Incoterm decides which of you is exposed to that.

The Incoterm is a cost allocation, not a formality

Under Incoterms 2020 the three rules that dominate bitumen trade are FOB, CFR and CIF. Under all three, risk passes to the buyer once the goods are on board at the port of shipment. What changes is who pays for the voyage: under FOB the buyer arranges and pays the ocean freight and takes the freight-market risk; under CFR the seller pays the freight but not the insurance; under CIF the seller pays freight and buys cargo insurance. A CIF number therefore looks larger than an FOB number for the same cargo and can still be cheaper landed.

Two details are worth knowing before signing. First, FOB, CFR and CIF were written for cargo handed over at the ship's rail, and the International Chamber of Commerce points containerised shippers toward FCA, CPT and CIP instead, because a container is handed to the carrier at a terminal days before it is on board. Using FOB for a container leaves a gap between the moment you lose control and the moment risk formally transfers. Second, the insurance floor differs by rule: under Incoterms 2020, CIF requires only the minimum cover of Institute Cargo Clauses (C), while CIP requires the wider Clauses (A). If you are buying CIF and expect all-risks cover, you must say so in the contract.

At the far end of the scale, DAP and DDP put delivery at destination on the seller, and DDP additionally puts import clearance and duty on the seller. For a market where the seller has no established customs presence, DDP transfers a risk that the seller cannot manage and the buyer can — which usually shows up as a worse price, not a better service.

The volatile lines

Ocean freight and its surcharges are the least predictable part of a landed tonne. Rates respond to vessel supply, port congestion, equipment availability and route risk, and surcharges such as bunker adjustment, war risk and congestion can be applied between booking and sailing. Product price moves with crude and heavy residue values. Packing tracks steel. Everything else on the table is comparatively stable. This has one practical consequence: ask how long a quotation is valid and what is fixed within it. A CFR offer with a firm freight component for a defined shipment window is worth more than a lower CFR offer that will be re-priced if the box is not booked immediately.

The step-change line: duty

Petroleum bitumen is classified under HS heading 2713.20, and most destinations apply national subheadings beneath it. Duty is stable until it is not — a tariff change, an anti-dumping measure or a change of preferential origin treatment can move landed cost overnight and by more than a freight swing. Confirm the full destination code and the applicable rate with a local broker before contracting, and check whether a certificate of origin gives access to a preferential rate under a trade agreement. That certificate is a cheap document with a large effect.

Demurrage and detention, and the difference between them

These two words are used interchangeably and are not the same thing. Demurrage accrues when a container stays inside the terminal beyond the free time allowed. Detention accrues when the container is out of the terminal, in your yard, beyond the free time allowed for returning it empty. Both are charged per container per day, both escalate in tiers, and free time varies by carrier, trade lane and port. Confirm the free time in the booking rather than assuming a market norm, and remember that on a 70-container shipment a few idle days multiply by seventy.

For a bulk parcel the equivalent exposure is laytime and vessel demurrage under the charter party. If the shore tank cannot take the parcel at the agreed rate, or the discharge line stiffens, the vessel waits and the clock runs at a daily rate that dwarfs container demurrage.

The causes are boringly consistent: documents presented late or with discrepancies, a customs classification query, a missing Safety Data Sheet, an import permit that had lapsed, or a receiving facility that had not emptied and heated its tank before arrival. Almost every one of them is fixed by preparation two weeks earlier, which is why the documentation sequence below is a logistics topic and not an administrative one.

Documentation

The document sequence, from booking to release

Documentation is the part of bitumen logistics that most often stops the cargo, and it is the part that costs nothing to get right in advance.

1. Pre-booking checks

Confirm the full destination tariff code beneath HS 2713.20 with a local broker, confirm any import permit or standards registration, and settle packing, container type and the Incoterm. Where product ships hot in a tank, confirm with the carrier whether it must be declared as an elevated-temperature liquid under the IMDG Code — bitumen carried at or above 100 °C is treated differently from drummed product at ambient.

2. Verified gross mass

Under SOLAS Chapter VI Regulation 2 the shipper must declare a verified gross mass for every packed container before it can be loaded. For bitumen this is straightforward — net weight plus packing plus container tare — but a missing or late VGM will hold the box at the terminal.

3. Loading, inspection and evidence

Weighbridge tickets or tank gauging, third-party inspection covering quality, quantity and packing condition, sealed retained samples held by both parties, seal numbers recorded on the packing list, and photographs of the stow. This is the evidence base for any later claim, and it cannot be recreated afterwards.

4. The document set

Bill of lading, commercial invoice, packing list, batch Certificate of Analysis, Technical Data Sheet, Safety Data Sheet, certificate of origin and the inspection certificate. The description of goods, the quantity, the unit and the packing must read identically on every one of them.

5. Bank presentation

Where a letter of credit is used, presentation is governed by UCP 600 and the bank has up to five banking days to examine the documents. A discrepancy is not a technicality — it delays release, and the free-time clock at destination does not pause while it is corrected.

6. Arrival, clearance and discharge readiness

Duty paid, delivery order issued, haulage booked, and the receiving facility genuinely ready: tank empty and hot, melter serviced, yard clear. Reconcile quantity and quality against the load-port certificates while the retained samples and the claim period are still live.

Buyer questions

Frequently asked questions about bitumen logistics and shipping

What are the shipping options for bitumen?

Three. Containerised solid packing — new steel drums or one-tonne jumbo and poly bags — inside a standard 20-foot container. Insulated tank containers, often called bitutainers, carrying 20 to 25 MT each and moving on the same liner services. And bulk parcels on vessels with insulated, coil-heated cargo tanks, typically from 1,000 MT upward, discharged into a heated shore tank. The right choice is set by what equipment exists at the receiving end.

How many tonnes of bitumen fit in a 20-foot container?

The packing sets the tonnage, not the box. A 20-foot container takes 80 drums — ten along, four across, two tiers — so the load is 12 MT on a 150 kg fill, 14.4 MT at 180 kg and 14.8 MT at 185 kg. One-tonne bags stow ten down and ten on top: 20 bags, 20 MT. A tank container or bitutainer holds 20 to 25 MT with no packing at all. None of those loads approaches the plated payload of the container, so the figures that actually decide the fill are the two-tier stack limit and the road weight limit at destination.

What is a bitutainer and how is it discharged?

It is an insulated tank built into a standard 20-foot ISO frame, fitted with a heating system and a bottom discharge outlet, carrying 20 to 25 MT. At destination the product is reheated using the unit's own heating system until it is pumpable, then discharged through the bottom outlet by pump or gravity into a heated receiving tank. Reheating a full cold unit is a matter of days rather than hours, so it must be started before the plant needs the binder.

Does bulk bitumen arrive hot enough to pump?

It should. On a bulk vessel the cargo tanks are insulated and heated for the whole voyage, and discharge normally takes place in the 130–160 °C range, which is the practical pumping window for a paving grade. If cargo heating has failed or been reduced in transit, the parcel will discharge slowly and vessel demurrage starts to accrue. Ask for temperature records covering the voyage, not just a load-port figure.

Is bitumen classified as dangerous goods for sea freight?

Solid bitumen in drums or bags at ambient temperature is not normally treated as dangerous goods. Bitumen carried in a tank at or above 100 °C falls under the IMDG Code provisions for elevated-temperature substances and is declared accordingly. The distinction is the temperature at which it travels, not the product. Confirm the treatment with the carrier at booking, and have the Safety Data Sheet available in any case, since destination customs and terminals increasingly ask for it.

What makes up the landed cost of a tonne of bitumen?

Product, packing, inland haulage at origin, terminal handling and stuffing, export documentation and inspection, ocean freight and its surcharges, marine insurance, destination terminal handling, import duty and taxes, inland delivery, and the cost of discharging and melting the product at your end. Any demurrage or detention sits on top. Comparing offers on product price alone is how buyers end up paying more for the cheaper tonne.

Which parts of the landed cost are volatile?

Ocean freight and freight surcharges above all, since rates and bunker, congestion or war-risk surcharges can move between booking and sailing. Product price moves with crude and heavy residue values, and packing tracks steel. Terminal handling, documentation and inspection are broadly fixed. Import duty is stable until a policy change moves it in a single step. Demurrage is the exception — high when it appears, and avoidable.

What should be done if hot bitumen contacts skin during discharge?

Cool the affected area with clean cold running water for at least 20 minutes. Never peel or solvent-strip bitumen that has adhered to the skin — removal is a clinical decision and the adhered layer is protecting the wound underneath. Get medical attention and take the Safety Data Sheet with the casualty. Handling hot binder is where most bitumen injuries occur, so brief the discharge crew before the cargo arrives, not on the day.

QC
How this page is maintainedLoading figures on this page are the standard quantities used across this site and hold for common drum and bag dimensions; the container mass limit is taken from ISO 668 and the verified gross mass requirement from SOLAS Chapter VI Regulation 2. Incoterms references are to the Incoterms 2020 rules published by the International Chamber of Commerce, and documentary credit practice to UCP 600. Freight rates, surcharges, free time, duty rates and terminal tariffs are market and jurisdiction specific, change frequently, and are deliberately not quoted here as figures. Nothing on this page overrides the carrier's booking terms, the charter party or the sales contract. If you find a statement here that conflicts with a current rule or standard, tell us and we will correct it.